CAMEO+ eventINFRASTRUCTURE2026-04-16馃嚭馃嚫
Southwest Pennsylvania power lines proposed to supply data centers in Virginia
source: NextEra Energy Transmission MidAtlantic Inc. -> target: Northern Virginia data center sector
On 2026-04-16, NextEra Energy Transmission MidAtlantic Inc. said it is seeking eminent domain rights in Pennsylvania for the MidAtlantic Resiliency Link, a planned high-voltage transmission line. The 107-mile project would run from southwestern Pennsylvania through West Virginia and Maryland to Northern Virginia to supply electricity to data centers.
0.31Significance4.0Magnitude0.6Systemic0.6Market1Articles
Location
Dunkard Township, Greene CountyPennsylvaniaNorth AmericaUnited StatesNorth America39.818, -80.422
Story Links